UPPER CUMBERLAND – The Tennessee Department of Transportation (TDOT) and several local governments have significant highway construction going on throughout the Upper Cumberland region that will drastically impact travelers. The following are the traffic advisories for construction throughout the Upper Cumberland for April 30-May 6, listed by county and an estimated completion date.
Interstate Construction
CUMBERLAND COUNTY I-40 Construction of a truck climbing lane EB near MM 339, including grading, drainage, and paving: Construction signs, guardrail (westbound), and portable barrier rail (eastbound) have been installed on I-40. The contractor continues grade work and will be placing base stone behind portable barrier rail. Motorists should use caution and be aware of construction personnel in the work zone and equipment that will be entering/exiting the roadway. Estimated project completion date is September 2020.
CUMBERLAND COUNTY I-40 Resurfacing from the SR-101 ramp (LM 18) to east of SR-1 (US-70) (LM 24.6): The I-40 eastbound and westbound bridges at MM 326.5 in Cumberland County will be reduced to one lane during nighttime hours during this period. The contractor will be performing bridge repair work on each bridge. THP has been requested to assist with traffic control. Estimated project completion date is October 2020.
CUMBERLAND COUNTY TDOT Maintenance on I-40 westbound from MM 335.6 to MM 335.7: On 05/06/20 between 7 AM and 12 PM, crews will be spot paving on I-40 Westbound near MM 335.6.
PUTNAM COUNTY TDOT Maintenance on I-40 westbound at MM 298.7: On 05/06/20 between 12 PM and 4 PM, crews will be spot paving on I-40 around MM 298.7.
PUTNAM COUNTY Utility Work on I-40 in both directions from MM 20.70 to MM 20.70: A THP rolling road block will occur on I-40 from E. Spring Street to S. Willow Avenue. Motorists should be prepared to stop and be alert of all traffic signage, personnel, and equipment. This rolling road block will take place between 9:30 AM and 11:30 AM on 05/06/20.
State Road Construction
CANNON COUNTY Relensing of snowplowable pavement markers on various Interstate and State Routes: The contractor will be performing temporary lane closures to replace snowplowable pavement markers on various routes throughout Cannon County. Routes include SR-1 LM 0.00 – LM 5.78, SR-1 LM 7.37 – LM 14.82, SR-53 LM 0.00 – LM 24.08, SR-64 LM 0.00 – LM 9.11, SR-96 LM 0.00 – LM 4.96, SR-99 LM 0.00 – LM 1.36, SR-145 LM 0.00 – LM 3.65, SR-146 LM 0.00 – LM 9.51, SR-281 LM 0.00 – LM 4.18, and SR-281 LM 4.50 – LM 6.07. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is November 2020.
CUMBERLAND COUNTY Utility Work on SR-1 (WEST AVE.) in both directions from LM 14.17 to LM 14.63: Mobile lane closures will occur in both directions between Stanley Street and just beyond Park Street as crews transition the work zone. Signage, cones, and flaggers will be present between 8 AM to 3 PM with an estimated completion of 05/06/20.
CUMBERLAND COUNTY SR-1 (US-70) Emergency slope stabilization near LM 26.6: Construction signs, portable barrier rail, and temporary traffic signals have been installed. SR-1 (US-70) will be reduced to one lane between Godsey Road and Renegade Mountain Parkway while slope stabilization is in process. Motorists should exercise caution and pay attention to temporary traffic signals as they travel through the work zone.
CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: Motorists should use caution while driving along Peavine Road and be alert for shifts in traffic patterns. The posted speed limit has been reduced from 45 MPH to 35 MPH within the work zone. Base stone and paving have resumed, and temporary lane closures and/or traffic stoppages may be needed as construction activities continue. Motorists should reduce speed on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway. Estimated project completion date is November 2020.
DEKALB AND WARREN COUNTY SR-56 Construction of bridges and paving from south of Warren-Dekalb County line to East Bryant St: The contractor will continue installing concrete box culverts and drainage structures. Grade work and utility work on the new roadway alignment are ongoing. No change in traffic patterns, traffic is still using the existing SR-56, however, motorists are advised to use caution and watch for construction equipment adjacent to roadway. Flaggers may be present to move equipment across roadway, unload equipment, or complete utility work. Estimated project completion date is May 2022.
FENTRESS COUNTY SR-52 Resurfacing (microsurfacing) from SR-296 (LM 17.6) to the Morgan County line (LM 27.9), including bridge deck and expansion joint repair; SR-296 resurfacing (microsurfacing) from SR-28 (US-127) (LM 0) to SR-52 (LM 3); and SR-28 (US-127) resurfacing (microsurfacing) from south of Airport Road (LM 13.3) to near the Old US-127S ramp (LM 16.9): The contractor is scheduled to begin paving operations on 05/11/20 on SR-52 from LM 17.6 to 27.9 and on SR-296 from LM 0.0 to LM 3.0. During this work, the contractor will use a mobile operation and will have the roadway reduced to one lane. Flaggers will be used along with a pace vehicle to control the flow of traffic through the work zone. Estimated project completion date is September 2020.
FENTRESS AND OVERTON COUNTY SR-85 Emergency slide repairs at various locations: The contractor continues work on the Overton County side of SR-85 and the road remains closed from LM 17.5 to LM 22.2. This closure will remain in effect until the project completion scheduled for 09/30/20. The Fentress County portion of SR-85 remains open to through traffic. A detour route remains in place for Overton SR-85 and motorists are encouraged to continue using the detour route until the road is opened. Estimated project completion date is September 2020.
JACKSON COUNTY SR-85 Resurfacing (microsurfacing) from the Smith County line (LM 0) to SR-56 (LM 15.3) and SR-262 resurfacing (microsurfacing) from the Macon County line (LM 0) to the Cumberland River Bridge (LM 7.5): The contractor will begin guardrail work on 05/04/20. During this work, one lane will be closed at various locations. Flaggers and advanced warning signs will be utilized for this work. The contractor is scheduled to begin paving work on 05/12/20 and will use flaggers to control the flow of traffic through the work zone. Motorists are encouraged to use caution in the work zone and obey posted speed limits. Estimated project completion date is September 2020.
OVERTON COUNTY SR-294 Bridge repair over Big Eagle Creek: The lane closure at LM 1.39 remains in place and will last until project completion scheduled for 06/15/20. The contractor has begun work on Phase 2 of the project and a temporary signal system remains in place to allow traffic through the work zone. Motorists are encouraged to use caution and move slowly through the work zone when the signal light allows. RESTRICTIONS: Loads wider than 9.5′ should seek alternate route. Estimated project completion date is June 2020.
OVERTON COUNTY S.I.A. Grading, drainage and paving on Oak Hill Road from Rickman Road to near SR-111: The contractor currently has Oak Hill Road closed to traffic. This road closure is scheduled to remain in place until project completion scheduled for 06/30/20. The closure of Oak Hill Road will begin just past the Tanimura Plant entrance and end at first entrance of Fitzgerald’s Plant. During this closure, motorists wishing to access Tanimura Plant should do so from SR-111 side; motorists wishing to access Fitzgerald’s should do so from Old SR-42/Rickman Road. A detour route will be in place along SR-293 to allow motorists to bypass Oak Hill Road. Estimated project completion date is June 2020.
PUTNAM COUNTY – Cookeville South Willow Ave. from State St. to I-40: Lane closures will occur between I-40 and State Street with signage, barrels and cones. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Traffic may be reduced to a single lane in some locations from 9 AM to 3 PM, Monday through Friday with estimated completion date of 06/30/20.
PUTNAM COUNTY Utility Work on SR-111 (STATE HWY. 111) in both directions from LM 2.55 to LM 2.55: A THP rolling road block will occur on SR 111 from Salem Road to SR 136. Motorists should be prepared to stop and be alert of all traffic signage, personnel, and equipment. This rolling road block will take place between 9:30 AM and 10:00 AM on 05/05/20.
PUTNAM COUNTY SR-136 Resurfacing from US-70N (SR-24) (LM 4.15) to north of Whiteaker Springs Road (LM 7): The contractor will begin milling operations during the day, resulting in daily lane closures from 12th Street (LM 5.35) to north of Whiteaker Springs Road (LM 7.00). Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.
SMITH COUNTY, Emergency slope stabilization on U.S. 70 (S.R. 24) near L.M. 12.95: From now through July 2020, U.S. 70 (SR 24) is reduced to one 11′ lane. Temporary traffic signal in place for traffic control.
VAN BUREN COUNTY SR-30 Slope stabilization in VanBuren County near LM 16.1: The contractor is working on SR-30 North from LM 15.9 to 16.3. The roadway will be reduced to one lane controlled by a traffic signal. Large trucks heading West on SR-30, down the mountain are encouraged to use extreme caution. Estimated project completion date is June 2020.
WARREN COUNTY SR-288 Construction of a concrete bulb-tee beam bridge over Collins River, including grading, drainage and paving: Both lanes of the bridge are now open. Motorists should use caution in the work zone and watch for workers. If necessary, flaggers may be present to complete any remaining work. Estimated project completion date is May 2020.
WHITE COUNTY Grading, drainage and paving at Airport Rd. leading up to Upper Cumberland Regional Airport: The contractor will be working on grading and drainage work along Technology Drive and Airport Road during this period. Temporary traffic stoppages may be needed as construction progresses. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.