UC Traffic Advisories Oct. 15-20

UPPER CUMBERLAND – The Tennessee Department of Transportation (TDOT) and several local governments have significant highway construction going on throughout the Upper Cumberland region that will drastically impact travelers. The following are the traffic advisories for construction throughout the Upper Cumberland for Oct. 15-20 listed by county and an estimated completion date.

Interstate Construction:

I-40 Cookeville to Nashville

No construction scheduled

I-40 Cookeville to Knoxville 

PUTNAM COUNTY I-40 EB bridge repair and resurfacing from west of Falling Water River Bridge (MM 291) to the ramp from SR-24 (US-70N / MM 300): The contractor will be performing nightly lane closures Sunday through Friday from 7 PM – 6 AM. Contractor will be placing shoulder stone and pavement markings throughout project. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

CUMBERLAND COUNTY I-40 resurfacing from the SR-101 ramp (MM 321) to east of SR-1 (US-70) (MM 329): There will be lane closures on I-40 both eastbound and westbound near MM 326 for bridge repairs. One lane will remain open in each direction and THP will assist with traffic control.

ROANE COUNTY, I-40 West between Mile Markers 340 and 344: Motorists should be alert for possible lane closures at various times through this slope stabilization project. Motorists should be alert for workers present, reduced speeds, lane shifts, and use extreme caution through this area.  

ROANE COUNTY, I-40 West near Mile Marker 358.9: Motorists should be alert for possible lane closures between the hours of 8 p.m. and 6 a.m. the following morning as crews perform guardrail repairs.  Motorists should be alert for workers present, expect possible delays, and use caution through this area.

Regional (Multi-county) Road Work

CANNON AND WARREN COUNTY SR-1 (US-70S) bridge repair and paving from east of Lincoln Lane (LM 11) in Cannon County to Robinson Road (LM 9.4) in Warren County:  The contractor to set up daily lane closures on SR-1 for the construction of ADA ramps, micro-surfacing, and painting. Motorists should use caution and be aware of construction equipment and personnel.

DEKALB AND WARREN COUNTY SR-56 Construction of bridges and paving from south of Warren-Dekalb County line to East Bryant St: The contractor will continue installing concrete box culverts and drainage structures. Grade work, bridge work, paving operations, and utility work on the new roadway alignment are ongoing. Traffic is still using the existing SR-56; however, motorists are advised to use caution and watch for construction equipment adjacent to roadway. Flaggers may be present to move equipment across the roadway, unload equipment, or complete utility work. The contractor is currently performing grade work at various locations throughout the project. A traffic shift in Smithville will remain from Vaughn Lane to the end of project to allow the contractor to complete work. There will be a temporary diversion for Ferrell Rd, and one remains in place for Williams Road to allow contractor to construct new alignment. The speed limit has been reduced to 45 mph in the construction zone. Motorists should use caution in this area and watch for flaggers and construction equipment.

PUTNAM AND WHITE COUNTY SR-111 resurfacing from south of Overpass Road (LM 13.5) in White County to north of SR-136 (LM 2.0) in Putnam County: The contractor will be resurfacing the roadway throughout the project, resulting in daily lane closures. Motorists should be aware of all construction equipment and personnel when traveling through the work zone.

PUTNAM AND WHITE COUNTY SR-135 resurfacing in White County to west of Grider Road in Putnam County, and on SR-136 in White County from near SR-135 to SR-111: The contractor will be installing pavement markings in Putnam and White County along SR-135 and White County along SR-136. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

State Road Construction

CANNON COUNTY The miscellaneous safety improvements including high friction surface treatment (HFST) on various local roads: The contractor to set up daily lane closures on various Cannon County roads (Hill Creek Road, Eugene Reed Road, Short Mountain Road, Pleasant View Road, Old McMinnville Highway and Ivy Bluff Road) for the installation of various safety improvements. Motorists should use caution and be aware of construction equipment and personnel.

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): Construction signs have been installed with erosion control activities and clearing on going. The contractor has started road and drainage activities which may require some drilling and blasting. Utility relocations for gas, water, sewer, and electric are in progress. Temporary lane closures or traffic stoppages will be necessary as construction activities continue. Motorists should use caution while traveling through the work zone.

CUMBERLAND COUNTY SR-298 (GENESIS RD.) Utility Work both directions from LM 0.17 to LM 1.68: Mobile lane closures along SR-298 between I-40 and Industrial Blvd. Motorists should use caution and be aware of personnel and equipment when traveling through the work zone. Support vehicles, signage and flaggers will be present between 9 AM and 2:30 PM starting 10/07/21 through 10/27/21. 

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road/LM 4.6) in Crossville: Construction signs are installed. The contractor is installing erosion control measures ahead of road and drainage activities. Utility relocation activities for gas, water and sewer are in progress. Construction activities may require temporary lane closures and/or traffic stoppages.

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor has begun clearing operations, installing erosion control measures, and water line relocation. Intermittent lane closures and flagging operations are expected. Intermittent blasting operation has begun resulting in temporary road closures. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

DEKALB COUNTY SR-56 (COOKVILLE HWY.) TDOT Bridge Inspection both directions at LM 15.4: Bridge inspection will be continuing its 2-year inspection on the SR-56 bridge over the Caney Fork River at LM 15.4 from 8 AM until 2 PM 10/18/21, 10/19/21, and 10/20/21.

FENTRESS COUNTY SR-28 (US-127) resurfacing from north of S.R.52 (LM 19.8) to north of Kip Chase Rd (LM 23.1) and SR-154 from Millsap Ave (LM 1.4) to east of Louvaine Rd (LM 6.3): The contractor is currently performing paving operations on SR 28. During this work, one travel lane will be closed, and the contractor will utilize flaggers and advanced warning signs to control the flow of traffic through the work zone. The contractor also will be paving on SR154, and one lane will be closed. Flaggers will be used to control the flow of traffic through the work zone. Motorists are encouraged to use caution and obey posted speed limit through the work zone.

FENTRESS COUNTY SR-62 resurfacing from east of SR-28 (US-127 / LM 5.8) to the Morgan County line (LM12.7): The contractor has completed resurfacing operations and will be on site intermittently to perform punch list work. Motorists are encouraged to use caution and obey posted speed limit through the work zone.

JACKSON COUNTY SR-56 resurfacing from north of Riley Creek Road (LM 17.2) to the Macon County line (LM 27.3): The contractor will be on site intermittently performing punch list work. Motorists should obey posted speed limit and use caution through the work zone.

OVERTON COUNTY SR-111 resurfacing from south of East Volunteer Dr (LM 9.4) to SR-294 (LM 14.0) and on SR-52 from near SR-111 (LM 10.2) to north of SR-52/SR-85 (LM 11.0): The contractor will set up nightly lane closures from 7:00 PM to 6:00 AM to continue with resurfacing operations. Paving on SR111 is scheduled to begin on Sunday, 10/10 and will continue for the coming weeks. The contractor will also run concurrent operations during the daytime and will be paving after 8:00 AM beginning 10/12 on SR 52 and the northern section of SR111. During these operations, the contractor will place advanced warning signs and will utilize flaggers to control the flow of traffic through the work zone. Motorists are encouraged to use caution and obey posted speed limit through the work zone.

PICKETT COUNTY SR-325 resurfacing from Star Point Road to SR-111; on SR-111 from north of Jim Beaty Road to Pendergrass Road and from north of SR-295 to south of Red Hill Church Road: The contractor has completed resurfacing and bridge repair operations. The contractor will be on site intermittently to perform punch list work. Motorists are encouraged to use caution through the work zone and obey posted speed limit.

PUTNAM COUNTY SR-56 repair of the bridge over I-40 (LM 0.5): The contractor will be on site the week of 10/10/21 to install a temporary signal system to control traffic from the I-40 offramps as well as SR-56. The signal will flash for a period of three days prior to beginning stop and go operations. Once the signal is in operation, a lane closure will be in effect on SR-56 across the I-40 overpass bridge until project completion on 11/30/21. Motorists are encouraged to use caution and be prepared to stop as they approach the work zone.

PUTNAM COUNTY SR-135 (Burgess Falls Road) grading, drainage, signals and paving at the intersection of West Cemetery Road (LM 6.6): The contractor continues their roadside operations and paving along SR-135 and West Cemetery Road, resulting in daily lane closures. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

PUTNAM COUNTY SR-24 (US-70N) slide repair near LM 30.1: The contractor has installed barrier rail and will continue retaining wall construction. Traffic will be reduced to one lane and controlled by temporary traffic signals at each end of the project. Motorists should be prepared to stop when traveling through the work zone.

PUTNAM COUNTY SR-290 resurfacing from Shipley Road (LM 1.6) to SR-135 (LM 6.4): The contractor will be installing signs and will begin milling and ADA ramp operations. Motorists should be prepared to stop and be aware of all construction equipment and personnel.

SMITH COUNTY SR 24Resurfacing on US 70Daily, 8 a.m. – 2:45 p.m., SR 24 near SR 264 to Putman County line will have intermittent lane closures for resurfacing activities.  

Michelle Price is the former managing editor of the Upper Cumberland Business Journal and can be reached via email. Send an email.