UC Traffic Advisories July 1 – 7

UPPER CUMBERLAND – The Tennessee Department of Transportation (TDOT) and several local governments have significant highway construction going on throughout the Upper Cumberland region that will drastically impact travelers. The following are the traffic advisories for construction throughout the Upper Cumberland for July 1 – 7 listed by county and an estimated completion date.

The Tennessee Department of Transportation will suspend all construction-related lane closures on interstates and state routes beginning at 6:00 a.m. on Friday, July 2 through 6:00 a.m. on Tuesday, July 6 to provide maximum roadway capacity for holiday travelers.

Interstate Construction:

I-40 Cookeville to Nashville

PUTNAM COUNTY I-40: There will be an area wide sweeping operation on selected regional state routes and interstates. This activity will be supported by a mobile lane closure. Hours of activity are Sunday through Thursday night between 8 PM and 6 AM during this reporting period. The drain cleaning operation will be having intermittent lane closures on SR153, SR111, I24 MM132.8-134.3 and I40 MM269.6-273. During this reporting period, the contractor will only be working Thursday Night.

PUTNAM COUNTY I-40 resurfacing from east of SR-56 (MM 281) to west of SR-136 (MM 287): Contractor will be performing nightly lane closures Sunday through Thursday from 7 PM – 6 AM. Work will consist of milling and paving operations. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

WILSON COUNTY, Emergency Bridge Repair on I-40 at SR 171 (Mt Juliet Road)Now through July 14 (continuous), There will be a lane closure on I-40 West at mile marker 226 and on Mt Juliet Road North over the interstate for emergency bridge repair.

WILSON COUNTY, Bridge Widening on SR 171 over I-40: Nightly, 8PM-5AM, There will be intermittent lane closures on I-40 in both directions, between mile markers 225 and 226, for the removal of existing bridge parapet.

WILSON COUNTY, Retracing of Pavement Markings on I-40: Nightly, 8PM-6AM, There will be moving lane closures on I-40 in both directions, between mile markers 222 and 225 and mile markers 231 and 240, for restriping operations.

I-40 Cookeville to Knoxville 

PUTNAM COUNTY I-40 resurfacing from east of SR-56 (MM 281) to west of SR-136 (MM 287): Contractor will be performing nightly lane closures Sunday through Thursday from 7 PM – 6 AM. Work will consist of milling and paving operations. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

PUTNAM COUNTY I-40 EB bridge repair and resurfacing from west of Falling Water River Bridge (MM 291) to the ramp from SR-24 (US-70N / MM 300): The contractor will patch potholes at night, which will require temporary lane closures from 7 PM to 6 AM Sunday night through Thursday night. Motorists should be prepared for slower traffic and be alert to construction equipment and personnel entering and exiting the work area.

CUMBERLAND COUNTY I-40 repair of the bridges over SR-1 (US-70) at MM 328.5:  During this period, westbound and eastbound I-40 near MM 328 will have no scheduled lane closures. SR-1 (US-70) may be reduced to one lane with traffic signals near LM 24 at Crab Orchard, TN for bridge repair. Motorists should exercise caution and pay attention to the temporary traffic signals as they travel through the work zone.

ROANE COUNTY I-40 West between Mile Markers 340 and 344: Motorists should be alert for possible lane closures at various times through this slope stabilization project. Motorists should be alert for workers present, reduced speeds, lane shifts, and use extreme caution through this area.

ROANE COUNTY, I-40 East near Mile Marker 353:  Motorists should be alert for possible lane closures between the hours of 7 p.m. and 6 a.m. the following morning as crews set portable barrier rails through this slope stabilization project.  Motorists should be alert for workers present, slow traffic, and use extreme caution through this area.

Regional (Multi-county) Road Work

REGION 2 The random on-call pavement marking on various interstate and state routes: Contractor will be retracing pavement markings on various interstate and state routes in Clay, Jackson, Overton, Pickett, Putnam, Dekalb, White and Cumberland counties. Work will be performed using mobile operations. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

DEKALB AND WARREN COUNTY SR-56 Construction of bridges and paving from south of Warren-Dekalb County line to East Bryant St: The contractor will continue installing concrete box culverts and drainage structures. Grade work, bridge work, paving operations, and utility work on the new roadway alignment are ongoing. Traffic is still using the existing SR-56; however, motorists are advised to use caution and watch for construction equipment adjacent to roadway. Flaggers may be present to move equipment across roadway, unload equipment, or complete utility work. The contractor currently performing grade work inside Smithville City Limits between Dearman Street and East Bryant Street. A traffic shift in this area will remain to allow contractor to complete work. A diversion remains in place for Williams Road to allow contractor to construct new alignment. The speed limit has been reduced to 45 mph in the construction zone. Motorists should use caution in this area and watch for flaggers and construction equipment. The contractor will not interfere with traffic flow during 07/02/21 through 07/05/21.

PUTNAM AND WARREN COUNTIES longitudinal joint stabilization on various state routes: During the daytime, the contractor will have short term lane closures on various routes in Putnam on SR-111, Warren on SR-55, and Grundy SR-50. During this time one lane of traffic will be closed while contractors are present. Please use caution when traveling through the area.

State Road Construction

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): Construction signs have been installed with erosion control and clearing activities in progress. Utility relocation for the gas line is in progress. Temporary lane closures or traffic stoppages will be necessary as construction activities continue. Motorists should use caution while traveling through the work zone.

CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: Motorists should use caution while driving along Peavine Road. The posted speed limit from I-40 to Tuttle Lane is now 45 MPH. The existing speed limit within Fairfield Glade remains at 30 MPH. The newly installed traffic signals at Stonehenge and Eagle Lane are in operation. Temporary lane closures and/or traffic stoppages may be needed as the contractor completes punch list activities. Motorists should reduce speed on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway.

DEKALB COUNTY SR-26 (US-70) construction from near SR-53 (LM 2) to near SR-96 (LM 6.1):Contractor has begun clearing operations and installing erosion control measures. Intermittent lane closures and flagging operations are expected. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

PUTNAM COUNTY SR-135 (Burgess Falls Road) grading, drainage, signals and paving at the intersection of West Cemetery Road (LM 6.6): Contractor continues their roadside grading operations and will have a road closure in place on Meadow Wood Drive beginning 07/06/21. A signed detour is in place during this time via Colonial Drive. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

PUTNAM COUNTY SR-24 (US-70N) slide repair near LM 30.1: The contractor has installed barrier rail and began excavation work. Traffic will be reduced to one lane and controlled by temporary traffic signals at each end of the project. Be prepared to stop when traveling through the work zone.

SMITH COUNTY, SR 25 Rockfall MitigationFrom now through September 2021, SR 25 north of the SR 80 intersection is reduced to one lane for a rockfall mitigation project.

WARREN COUNTY The random on-call signing on various State Routes: During the daytime, the contractor will be setting up shoulder closures at various locations in Sequatchie, Marion, Warren, Coffee, Franklin, and Grundy Counties to install new signs. A truck mounted attenuator will be on site during these closures.

VANBUREN COUNTY SR-111 resurfacing (microsurfacing) from the Sequatchie County line (LM 0.00) to north of Feedstore Drive (LM 12.51): The contractor has begun resurfacing operations on SR-111 from the Sequatchie County line to Log mile 12.51 in Van Buren. One lane will be closed while resurfacing operations are taking place. Please use caution when traveling through the area.